Power restored to parts of Abuja following emergency substation repairs​

ABUJA — Power supply has been restored to parts of Nigeria’s capital, Abuja, following the completion of emergency maintenance at the Kukwaba transmission substation, grid operators say.​

The Transmission Company of Nigeria (TCN) confirmed that engineers successfully re-energised a 60MVA power transformer at 20:31 local time on Thursday, September 24.​

The transformer had been isolated earlier in the afternoon to allow technical crews to replace a faulty blue-phase circuit breaker pole on the 33kV L31 feeder.​

The maintenance work temporarily cut power to customers supplied by the Abuja Electricity Distribution Company (AEDC).​

In a statement released on Friday, TCN management confirmed that all repair work was completed safely and thanked affected residents for their patience during the outage.