​Parts of central and southern Nigeria will experience temporary power outages on Tuesday as engineers carry out annual preventive maintenance at a key transmission hub, the state-owned grid operator has announced.

​The Transmission Company of Nigeria (TCN) said in a statement that the scheduled work at the 330/132kV Ajaokuta Transmission Substation will run from 09:00 to 16:00 local time (08:00 to 15:00 GMT).

​Engineers will service a 162MVA power transformer along with associated switchgear and support equipment to help ensure long-term reliability of the supply network.

​The interruption will affect local distribution networks managed by both the Abuja Electricity Distribution Company (AEDC) and the Benin Electricity Distribution Company (BEDC).

Areas Affected

  • AEDC Customers: Towns including Ekirin, Omuo, Ibillo, Akoko, Ogala, Ikare, Magongo, Okene Town, Ayere, Kabba, and surrounding communities.
  • BEDC Customers: Communities including Okpella Town, Ososo, Uluoke, Iyora, Apana, Okpekpe, Arigidi, Ikare Town, Lampese, Igara, and Oka.
  • Industrial Facilities: Major industrial consumers—including the BUA Cement Company, West African Fertilizer Company, Dibeks Milling Company, Edestein Company, and Freedom Group Company—will also face temporary supply disruptions.

​TCN stated that electricity supplies will be restored immediately once maintenance work concludes, apologizing to residential and commercial customers for the temporary disruption.